to disturb 10,000 sf or more of land (stripping or grading which affects more than 10,000 sf of ground surface within any parcel or any contiguous area) |
>
|
excavation or filling that exceeds a total of 300
cubic yards within any parcel or contiguous area |
>
|
site preparation on sites which exceed 15% slope or
result in slopes in excess of 15% (however, when this is the only threshold
met, the Director may deem small projects, which in his judgment do not present
an adverse environmental impact, as not meeting this threshold). |
|
|
For any questions about stormwater management reviews, please contact Don Spies, Facilities Engineer, at (315) 448-8210 or dspies@ci.syracuse.ny.us.
|
|
|
| Stormwater Review Process |
| A two-step review process is required before permits can be issued. |
|
|
1.
|
Drainage reports/SWPPP are reviewed by Engineering. This is a
technical review to assure that the reports are complete and conform to
City and NYSDEC requirements. When the Engineering Department is
satisfied, the applicant is notified. |
|
|
2.
|
Maintenance and Access agreements are prepared (see model
agreements below) attesting to the applicant’s planned maintenance and
the City’s ability to inspect the facilities. |
|
| a. |
The agreements and surety are submitted to
Law Department, and copies of the agreements are submitted to the Engineering
Department. |
b.
|
The Law and Engineering Departments conduct legal and technical reviews of the agreements. |
c.
|
When Engineering is satisfied, the City Engineer signs the agreements.
|
d.
|
The Law Department then notarizes the agreements and the applicant is notified.
|
e.
|
The applicant files the agreement with the County Clerk.
|
f.
|
The applicant provides the Permit Office with the County Clerk's receipt number.
|
|
|
|
| City of Syracuse's Stormwater Management Documents |
>
|
City of
Syracuse's Stormwater Management and Erosion Control Ordinance #53 |
>
|
City of Syracuse Building Code Chapter 17
|
>
|
City of Syracuse Draft Stormwater Facility Maintenance Agreement (rev. July 2009) and |
|
City of Syracuse Stormwater Control Facility Maintenance & Access Agreement (April 2009)
|
|
Agreements and surety submitted to Law Department (after Engineering
approval of Stormwater Facility Maintenance Agreement), then secondary
review by Engineering Department before Law Department notarizes and
agreement is filed with County Clerk. |
|
|
NYS DEC's Stormwater Construction Management Documents
|
>
|
NYS
DEC's Construction Stormwater Website |
>
|
NYS DEC's
Construction Stormwater SPDES Permit Application |
>
|
NYS DEC's
Construction Stormwater "Notice of Intent" |
>
|
NYS DEC's
Construction Stormwater "Notice of Termination" |
|
|
Related Stormwater Management Documents
|
>
|
NYS
Standards and Specifications for Erosion and Sediment Control |
>
|
NYS Stormwater Management
Design Manual |